Report

If a scroll bar appears below the following table, swipe the table to move left/right of the dashed line.
OFFICE OF THE UNDER SECRETARY FOR MANAGEMENT
Office of Management Policy, Rightsizing and Innovation
Financial and activity report submitted to the Office of Management and Budget under the American Recovery and Reinvestment Act
Week End Date: June 30, 2011
TAFS Award Type Total Obligations Total Gross Outlays Direct or Reimbursable Ordering TAFS
(19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act Contracts and Orders
(including modifications)
24,237,935 17,393,042 Direct
(19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act Other 508,642 446,300 Direct
(19-4519 \ X ) Working Capital Fund Other 305,995 222,004 Reimbursable (19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act
(19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act Other 919,860 915,866 Reimbursable [15-9-0700] Justice
(19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act Contracts and Orders
(including modifications)
147,171,111 130,094,278 Direct
(19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act Other 75,982 73,505 Direct
(19-4519 \ X ) Working Capital Fund Other 4,301,373 1,895,056 Reimbursable (19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act
(19-1079 2009 \ 2010) Construction, IBWC, Recovery Act Contracts and Orders
(including modifications)
219,135,523 162,107,484 Direct
(19-1069 \ 2009) Salaries and Expenses, IBWC Other 863,249 859,455 Direct
(19-4519 \ X ) Working Capital Fund Other 17,129 17,129 Reimbursable (19-0530 2009 \ 2010) Office of the Inspector General, Recovery Act
INTERAGENCY TRANSFERS TO DATE:
(19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act Interagency 64,944,043 4,699,435 Direct
(19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act Interagency 100,426,458 49,370,520 Direct
OFFICE OF THE INSPECTOR GENERAL SPENDING:
(19-0530 2009 \ 2010) Office of the Inspector General Contracts and Orders 1,713,437 1,258,548 Direct
(19-0530 2009 \ 2010) Office of the Inspector General Other 79,229 66,640 Direct
Total Obligations Total Gross Outlays
TOTALS: 564,699,964 370,805,008
MAJOR COMPLETED ACTIONS (Short bulleted list of the major actions taken to date.) MAJOR PLANNED ACTIONS (Short bulleted list of the major planned actions)
Data Center: The final piece of the ESOC West building shell has been installed. Data Center: The Department is on target to take delivery of the finished building in November. At that time IT work will begin. The data center will open for installation of Bureau servers in June 2012.