Financial and Activity Report Weekly Update: March 16, 2009
Report
OFFICE OF THE UNDER SECRETARY FOR MANAGEMENT
Office of Management Policy, Rightsizing and Innovation
Financial and activity report submitted to the Office of Management and Budget under the American Recovery and Reinvestment Act
March 16, 2009
Office of Management Policy, Rightsizing and Innovation
Financial and activity report submitted to the Office of Management and Budget under the American Recovery and Reinvestment Act
March 16, 2009
| No. |
Weekly Update Report Data (sheet 1 of 2) Version 1.1 |
||||||
| Agency Name: |
US Department of State |
||||||
| Week End Date: |
03/13/2009 |
||||||
| Submitter Name: |
Patrick F. Kennedy |
||||||
| Submitter Contact Info: |
Rachel Arndt (202) 647-1068 |
||||||
| Program Source/ Treasury Account Symbol: Agency Code |
Program Source/Treasury Account Symbol: Account Code |
Program Source/Treasury Account Symbol; Sub-Account Code (OPTIONAL) |
Program Description (Account Title) |
Total Appropriation |
Total Obligations |
Total Disbursements |
|
| 1 |
19 |
0112 |
Diplomatic and Consular Programs |
$90,000,000 |
$0 |
$0 |
|
| 2 |
19 |
1119 |
Capital Investment Fund |
$290,000,000 |
$0 |
$0 |
|
| 3 |
19 |
0530 |
Office of Inspector General |
$2,000,000 |
$0 |
$0 |
|
| 4 |
19 |
1079 |
International Boundary and Water Commission - Construction |
$220,000,000 |
$0 |
$0 |
|
| 5 |
Weekly Update Report Data (sheet 2 of 2) |
||||||
| 6 |
Short bulleted list of the major actions taken to date |
Short bulleted list of the major planned actions |
|||||
| 7 |
International Boundary and Water Commission (IBWC) - Concluded negotiations for geo-technical investigations under RFP 09-07 for Lower Rio Grande Valley Reach (Lateral A - Donna Pump) |
IBWC - Complete Procurement Strategy for entire plan |
|||||
| 8 |
IBWC - Developed preliminary procurement strategy for entire project plan |
IBWC - Issue award for Geo-Technical Investigations service contract of Lower Rio Grande Valley Reach (Lateral A - Donna Pump) on March 18, 2009 |
|||||
| 9 |
IBWC - Completed selection for 1 Term Engineering position. On-board/starts date is 03/16/2009 |
IBWC - Complete procurement packages by 03/31/2009 of all pre-construction activities (statements of work and estimates for geo-tech, environmental, and design work ) |
|||||
| 10 |
IBWC - Completed selection for 2 Term Contract Specialist positions. On-board/start dates projected for 03/23/2009 |
IBWC - Developing phased plan obligation plan of all planned levee work by procurement line item |
|||||
| 11 |
Consular Affairs - Met with General Services Administration (GSA) to discuss space issues in relation to passport facilities |
IBWC - Complete selection of second Term Engineering position on 03/16/2009 |
|||||
| 12 |
Office of the Inspector General (OIG) held discussions with GSA/OIG on tracking/oversight of construction-related funding transferred to GSA |
||||||
| 13 |
Foreign Service Institute started Vendor Pre-performance service survey for language classrooms and offices renovations for the purpose of establishing measurements, parts requirements and costs |
||||||
| 14 |
OIG provided initial plan for oversight to Rep. Darrell Issa (R-CA) |
||||||
[This is a mobile copy of Financial and Activity Report Weekly Update: March 16, 2009]