| No. | Weekly Update Report Data (sheet 1 of 2) Version 1.1 | ||||||
| Agency Name: | US Department of State | ||||||
| Week End Date: | 03/27/2009 | ||||||
| Submitter Name: | Patrick F. Kennedy | ||||||
| Submitter Contact Info: | Rachel Arndt (202) 647-1068 | ||||||
| Program Source/ Treasury Account Symbol: Agency Code | Program Source/Treasury Account Symbol: Account Code | Program Source/Treasury Account Symbol; Sub-Account Code (OPTIONAL) | Program Description (Account Title) | Total Appropriation | Total Obligations | Total Disbursements | |
| 1 | 19 | 0112 | Diplomatic and Consular Programs | $90,000,000 | $0 | $0 | |
| 2 | 19 | 1119 | Capital Investment Fund | $252,000,000 | $0 | $0 | |
| 3 | 19 | 0530 | Office of Inspector General | $2,000,000 | $0 | $0 | |
| 4 | 19 | 1079 | International Boundary and Water Commission - Construction | $219,650,000 | $0 | $0 | |
| 5 | Weekly Update Report Data (sheet 2 of 2) | ||||||
| 6 | Short bulleted list of the major actions taken to date | Short bulleted list of the major planned actions | |||||
| 7 | International Boundary and Water Commission (IBWC): Completed Environmental Assessment (EA): Improvements to the Rio Grande Rectification Project in El Paso and Hudspeth Counties, Texas and signed a Finding of No Significant Impact (FONSI), March 3, 2009 | IBWC: Three contracts ready for award pending receipt of advice of allotment | |||||
| 8 | IBWC: Hired second term engineer and two contract specialists (start date - March 29, 2009) | IBWC: Complete procurement packages by March 31, 2009 (Statement of Work and Independent Government Estimates for pre-construction activities) | |||||
| 9 | Data Center: Met with GSA to discuss possible sites for new data center | ||||||