Report

OFFICE OF THE UNDER SECRETARY FOR MANAGEMENT
Office of Management Policy, Rightsizing and Innovation

Financial and activity report submitted to the Office of Management and Budget under the American Recovery and Reinvestment Act
April 13, 2009

If a scroll bar appears below the following table, swipe the table to move left/right of the dashed line.
FINANCIAL AND ACTIVITY REPORT
Week End Date: April 10, 2009



AGENCY/BUREAU
TAFS
Sub-Account Code (OPTIONAL)
Total Obligations
Total Gross Outlays
(014-05) Department of State: Administration of Foreign Affairs
(19-0112 2009 \ 2010) Diplomatic and Consular Program - Recovery Act

0
0
(014-05) Department of State: Administration of Foreign Affairs
(19-1119 2009 \ 2010) Capital Investment Fund - Recovery Act

0
0
(014-05) Department of State: Administration of Foreign Affairs
(19-0530 2009 \ 2010) Office of the Inspector General - Recovery Act

0
0
(014-15) Department of State: International Commissions
(19-1079 2009 \ 2010) Construction, IBWC - Recovery Act

771,059
0
MAJOR COMPLETED ACTIONS (Short bulleted list of the major actions taken to date.)
MAJOR PLANNED ACTIONS (Short bulleted list of the major planned actions)
International Water and Boundary Commission (IBWC): Committed Purchase Request in the amount of $7,141,145 for design of Canalization segments in the Upper Reach
IBWC: Will conduct tour of levees being rehabilitated in Dona Ana County, NM with prior appropriations and with Recovery Act funding for Senator Udall and Congressman Teague at the Senator's request
IBWC: Committed Purchase Request in the amount of $28,605 for re-design of Hidalgo Phase I in the Lower Reach
IBWC: Award Task Order for aerial survey (Lidar) (est. week of 4/13/2009)
IBWC: Committed Purchase Request in the amount of $78,654 for design for Lateral A segment in the Lower Reach
IBWC: Award Task Order for re-design of Hidalgo Phase II segment in the Lower Reach (est. week of 4/13/2009)
IBWC: Committed Purchase Request in the amount of $2,985,089 for design of Rectification segment in the Upper Reach
Data Center: Begin development of Statement of Work to engage an IT integrator
IBWC: Awarded Task Order in the amount of $771,059 for geo-technical investigations for segments in the Lower Reach

Hard Skills Training Center: DOS Office of Real Property Management sent letter to GSA Office of Real Estate Aquisition formally requesting assistance in acquiring a site

Cyber Security: Met with Center for Security Evaluation to discuss tools to guard against and track cyber attacks

Data Center: Worked with GSA to assess additional sites identified as potential ESOC locations

IT Platform Modernization: Finalized specifications for upcoming equipment procurement

National Foreign Affairs Training Center: Initial quote for systems furniture to increase occupancy of eight (8) SLS office's from three to six personnel was received